Mitigation in the construction industry
The term ‘mitigate’ means to make less severe or serious.
This can be important in the construction industry in a number of different circumstances.
- In relation to project delays, it refers to minimising the impact of the risk event (an event or cause of delay or disruption). For example, acceleration might be used to mitigate a delay. Where there is a claim for an extension of time, the contractor may be required to mitigate the delay and any resulting loss, even where the fault is not their own.
- In terms of losses incurred, it can refer to claimant's duty to mitigate their loss. A claimant will generally not be allowed to recover damage which could have been avoided had the claimant acted reasonably. For more information see: Mitigation of loss.
- In relation to planning policy, planning obligations or planning conditions might be used to mitigate or compensate for the negative impacts of a development. For more information see: Planning obligation and planning condition.
- In terms of risks, a contingency plan might be enacted to mitigate project risks, such as adverse weather, industrial disputes and so on. For more information see: Contingency plan.
Mitigation strategies might also be used in relation to:
- Environmental impact.
- Loss of habitat.
- Carbon emissions.
- Flood protection.
- Duty to warn.
A handbook on environmental impact assessment, 4th edition, published by Scottish Natural Heritage in 2013, suggests that:
These are the measures taken to avoid, cancel or reduce adverse impacts of a project. They are:
- Avoidance measures: Designed to avoid or eliminate any adverse impacts arising in the first place, including alternative or ‘do nothing’ options;
- Cancellation measures: Designed to nullify or cancel out any adverse effects of a project before adverse effects are felt;
- Reduction measures: Designed to minimise or at least reduce adverse impacts remaining after avoidance and cancellation measures have been applied to a project.
Culvert, screen and outfall manual, (CIRIA C786) published by CIRIA in 2019, suggests that the mitigation hierarchy is typically:
NB Global Warming of 1.5 ºC, Glossary, published by the Intergovernmental Panel on Climate Change (IPCC) in 2018, defines mitigation (of climate change) as: ‘A human intervention to reduce emissions or enhance the sinks of greenhouse gases.’
[edit] Related articles on Designing Buildings
- Consequential loss.
- Planning condition.
- Planning obligation.
- Contingency plan.
- Risk.
- Environmental impact assessment.
- Relevant event.
- Extension of time.
- Duty to warn in construction.
[edit] External references
- Ref The Society of Construction Law Delay and Disruption Protocol, 2nd edition, published in February 2017 by the Society of Construction Law (UK).
Featured articles
Check out some of the best features and news from Designing Buildings as well as key stories from around the web.
Construction Management, 8 July
NEETs crisis drives interest in trades, but apprenticeships barriers remain.
Passive fire protection webinar
MEP services penetration seals.
Where its at podcast (and video) - The role of the Architectural Technologist as an Expert Witness.
More than 200 remarkable buildings added to SAVE’s Buildings at Risk register.
Government scraps pre-application consultation for Nationally Significant Infrastructure Projects.
Historic England and infrastructure
New projects offer opportunities for the historic environment and local communities.
Construction Management, 2 July
Construction deaths halve in two years.
Green Book changes to drive investment in all parts of UK.
Minimum energy efficiency standards (MEES)
CIAT briefing on response to consultations for privately rented non-domestic properties.
Connect, collaborate, shape the future
Registration now live for UK Construction Week Birmingham.
CIOB announces Saul Humphrey FCIOB as new President for 26/27 term.
A quick, simple, and zero-bills solution to prevent overheating.